The best time to get things done is during the 7th lunar month, it seems. Its when construction workers are the least busy because many Chinese are pantang and don't want to have projects during that period. Useful piece of info, especially if living in Penang. Knowledge is power.
Here is a pictorial update on the slow progress so far.
10th November: the remaining pile-caps in place, ground beams laid and the tractor clearing the site
24th November: The plumber has put this project on hold while he completes another project. But the sewage and drainage pipes have to be laid before the ground slab is poured. So work on the ground slab is suspended until the plumber returns. Meanwhile, the pillars at the back of the house has been erected.